Scope & Subcontractor Tender Package

Project Scope Definition, Takeoff Synchronization, and Subcontractor Bid Matrix.

CSI 02 41 16

Selective Demolition & Excavation

Takeoff: 1,450 SF (4" slab) | Depth: 28" lowered

• Sawcut and remove existing 4" unreinforced concrete basement slab (approx. 1,450 sq.ft) with electric or hydraulic saws to prevent CO toxicity indoors.

• Excavate basement floor to an average depth of 28 inches below existing floor elevation to achieve target 8'-6" clear basement ceiling height.

• Install temporary structural shoring posts and jacks supporting the existing 2-storey floor system prior to load-bearing partition demolition.

Demarcation & Inclusions: Disposal bin placements, site loading, and City of Toronto street permit coordination are included in contractor scope.
CSI 31 40 00

Structural Underpinning (1-2-3 / A-B-C Sequence)

Takeoff: 31 Pins (3'-6" max width each) | 30 MPa

• Sequentially excavate and cast 31 reinforced concrete underpinning pins around exterior foundation perimeter in strictly alternating sequence (Section 1, 2, 3 or A, B, C).

• No adjacent pins shall be excavated simultaneously. Concrete shall cure for a minimum of 48 hours prior to dry-packing.

• Place minimum 2" to 3" non-shrink structural dry-pack grout (min 50 MPa at 28 days) rammed between top of cured underpinning concrete and underside of existing rubble/concrete footing.

Inspection Hold Point: Structural Engineer of Record (P.Eng) must inspect every excavated pin prior to concrete pour.
CSI 03 30 00

Cast-In-Place Concrete & Moisture Protection

Takeoff: 1,450 SF Slab (4" 25 MPa) + Platon Membrane

• Supply and install interior 4" perforated weeping tile connected to existing or proposed sump pit, covered with 3/4" clear stone wrapped in filter geotextile.

• Install 10-mil polyethylene or 2" extruded polystyrene (XPS R-10) continuous sub-slab vapor barrier taped at all laps.

• Pour new 4" concrete basement slab with 25 MPa compressive strength, 5-7% air entrainment, smooth steel-troweled finish.